September 20, 2005 - We finally get started by digging the basement.
|
The hole is ready ...
|
September 22 - footings are poured
|

September 30 - the basement walls are poured
|

October 12 - Gravel is leveled over the area where the garage will be.
|

A view of the basement from the northwest - basement entry.
|
|

October 14 - putting in the floor joists...
|
and framing in the windows in the basement.
|
Getting ready to put in the floor...
|

Jeanine's
living room,
dining room & kitchen.
|

Judy's studio, entrance
and laundry room
|

October 20 - walls ready to go up.
|
|

October 20 - First wall is up.
|

October 22 - Almost all the walls are up now - view of back of house
|

r. to l. Jeremy's bedroom, front entrance & wall
between garage & house.
|

October 26 - Trusses are ready...
|

Master bedroom on right with living room on left.
|

View of dining room in far corner, kitchen on the left, stairwell,
far right has the two large windows on either side of where the
fireplace
will be.
|

October 26 - Garage walls are up and roof begun.
|

Inside framing is well underway.
|

October 27 - The crane showed up nice and early to lift the heavy
parts.
|

How long would this have taken without the machine's help?
|

From beginning to end, this took about 1 hour.
|

Daylight is arriving, as are the roof supports.
|

So exciting!
|

October 28 - now for the slower parts
|

The roofline takes shape.
|

November 1 - this side hasn't been sheeted yet...
|

but the east side has!
|

Still November 1 -- progress continues
|

November
4 - plumbing and heating are being installed.
|

Also November 4 - the 'returns' on the front roof line..
|

and shingles go on - brrrr! It was a cold day to work outside.
|

November 10 - Doors and windows were delivered...
|

and installed.
|

Click here for
a close-up of the front door.
|

November 24 - the furnace is temporarily rigged up in the basement.
|

Insulation of all the upstairs walls is almost complete.
|

Our new fireplace.
|

Tub in main bath upstairs is installed.
|

Nearly ready to blow insulation in the vaulted ceiling of the livingroom.
|

December 7 - Preparing the basement to pour the concrete floor.
|

December 8 - the cement truck arrives with cement for the basement floor.
|

All done!
|

Now the cement has to set.
|

December 12 - Our back deck is up.
|

December 13 - Soffits and fascia - back view
|

Soffits and fascia - front view
|

December 13 - gyproc going up...
|

through
the door...
|

and
onto the ceiling!
|

More work done in the basement - furnace work continues.
|

December 15 - Soaker bathtub installed in master bedroom...
|

and the basement framed.
|

Kayla's room on the left, doorway to Jeanine's room straight ahead,
and bathroom on the right.
|

December 16 - FINALLY! Paper and stucco wire is being put up.
|

The long wall behind the garage.
|

December 16 - Stairs to/from upstairs.
|

December 20 - Garage doors close in the house.
|

Looking across livingroom towards entrance and stairs to the basement.
|

Looking at niche for TV, fireplace and entrance to master bedroom.
|

December 22 - The gyproc is completed upstairs. This is the view
out the dining room window.
|

...and the vaulted ceiling.
|

Looking at master closet, doorway to master bath in middle and entrance
to the bedroom on the right.
|

Master bath tub.
|

Jeremy's room.
|

Main bathroom.
|

Andrew's bedroom.
|

January 6 - The front steps arrive.
|

First, the stair supports
|

Thank goodness for strong machines.
|

The front steps finally in place.
|

January 15 - Stucco wire almost complete.
|

Drywall is all up and taped.
|

Front-entry ready for paint.
|

January 16 - Insulation going in downstairs.
|

January 18 - Insulation completed.
|

January 24 - Master bedroom painted.
|

Livingroom with first coat of paint.
|

Accent wall in livingroom.
|

January 25 - Drywall up downstairs.
|

January 27 - Doors are ready to be hung.
|

February 1 - Closet custom shelves.
|

February 3 - Master bedroom door hung.
|

Cabinets delievered at last.
|

February 6 - Starting to install the cabinets
|

A closer look at the cabinets
|

February 7 - Kitchen cabinets installed.
|

February 12 - Bathroom counter.
|

Kitchen countertops.
|

Kayla's room.
|

February 16 - Don begins work on the fireplace.
|

February 17 - Fireplace built.
|

February 23 - Front entry niches ready for staining.
|

Feb. 24 - Crown molding ready for staining.
|

Stair railing up.
|

February 28 - Fireplace stained.
|

March 16 - Carpet all down in Jere's room.
|

Tile completed in front entry.
|

March 17 - Backsplash tiled in kitchen.
|

Linoleum laid in laundry room.
|

March 22 -- Main bathroom vanity & sink.
|

The main bathroom is nearly complete.
|

The dishwasher is installed.
|

The kitchen sink is ready to use. |

Tile is grouted in ensuite bathroom.
|

The vanity/sink in the ensuite bathroom. |

Don installs laminate flooring in Jeanine's apartment.
|

Track lighting, pot lights and chandeliers are installed. |

Just the beginning of laying the hardwood flooring in the living room. |

March 23 - Cement truck arrives to pour garage floor. |

Stan installs laminate flooring in studio. |

Carol helps Don install the completed niches. |

The hardwood floor is nearly complete and protected with foam.
|

The completed niches are wired, ready for lighting to be installed.
|

The pantry shelves are nearly ready to use.
|

March 27 - The stairs are carpeted.
|
Stan works at the fireplace hearth.
|

Jeanine's appliances are waiting...
|

for the cabinets to be installed.
|
Jeanine's cabinets in kitchen.
|

Upstairs, the kitchen stove and microwave are delivered and installed.
|

The kitchen floor tile looks so good.
|
The washer & dryer are moved from the rental house and installed.
|

March 28 - The basement bathroom is being completed.
|

The dishwasher is hooked up in the basement.
|
Upstairs, the dishwasher is ready for the electrician,
|

the fireplace is nearly complete,
|

and the garage is full of our boxes...
and saws for Don and Stan to
use.
|
Don built the steps and railing for the garage entry.
|

The stairs are sturdy and well-built.
|

Stan has completed the tile work in the studio bathroom.
|
March 30 - The house is finally ready enough so
we can move in. However, some things still remain to be finished.
|

April 12 - On the same day that the laundry room cabinets were delivered,
the fireplace people came to get the fireplace working.
|

Stan installed the doorlatch on the front door.
|
April 13 - The weather is perfect for putting the stone on the front
of the house.
|

Wow - it really looks nice!
|

April 21 - the fellows arrive to put the duradeck on the deck.
|
Whoops, I forgot - March 28 - General Appliance workers installed the
central vac system.
|

May 22 - Victoria Day Weekend - Lay's Stucco arrive to do the scratch
coat of stucco.
|

We never realized all the equipment and men that would be working on
our house.
|

Working on the upper peak takes special equipment and courage.
|

The men work all day as well as half of the next day to complete the
scratch coat.
|

June 1, 2 - We were away for the weekend when the crew showed up to complete
the stucco.
|
After the main color is completed, the accent color is applied.
|

This color is called 'Valley Wine'.
|
Click here to see neighbours house color.
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
To see pictures of the house after we moved in